Forney CT1 hot gas path inspection

Ironrock Energy Partnersfrom Get Work ↗
Mechanical · 1495 FM 460 S, Forney, TX 75126 · GE 7FA.05 (CT-1) · 2026-06-122026-07-10 · active
Execution phasemobilized 2026-06-12
Mobilize
Disassembly
Inspection
Repair
Reassembly
Test & commission
Demobilize
Phase 6 of 7 · Test & commission
Recent updates & change orders
Change order addedMechanical · Δ $210,000 cost $165,000 · approved41d ago
Baseline lockedvalue $2,850,000 · cost $2,389,500 · GP $460,50053d ago
Change orders1
CO CO-01Mechanical
Row 1 blade set replacement on borescope findings
$210,000
cost $165,000
crew hours pending
Estimate ledgerRevised GP$505,50016.5% GM 0.4 pts
DivisionOrig valueOrig GPOrig GMRev valueRev GPRev GMΔ GP
Mechanical
HGP inspection + component swap, CT-1
$1,900,000$342,00018.0%$2,110,000$387,00018.3%+$45,000
IC&E
Controls checkout + instrument recalibration
$550,000$82,50015.0%$550,000$82,50015.0%$0
Scaffolding
Access + insulation removal/reinstate
$400,000$36,0009.0%$400,000$36,0009.0%$0
Job total$2,850,000$460,50016.2%$3,060,000$505,50016.5%+$45,000
Turbine
GE 7FA.05 · CT-1linked to Radar
Labor hours — planned vs actual
CraftPlannedActualVariance% used
Controls / I&C Technician8070-1088%
Field Supervisor160120-4075%
Helper / Apprentice160140-2088%
Turbine Mechanic160120-4075%
Crew on this project (4)Bench Board
NameRoleDates%
Marcus WebbField SupervisorJun 12Jul 5100%
Ray StubbsTurbine MechanicJun 12Jul 5100%
Mike FerroControls / I&C TechnicianJun 22Jul 550%
Tyler InezHelper / ApprenticeJun 12Jul 10100%