Unit 3 HGP outage support

Riverbend Energy
Mechanical · 5000 Riverbend Way, Beaumont, TX 77705 · Siemens SGT6-5000F (U3) · 2026-07-202026-08-10 · active
Execution phasemobilized 2026-07-20
Mobilize
Disassembly
Inspection
Repair
Reassembly
Test & commission
Demobilize
Phase 1 of 7 · Mobilize
Recent updates & change orders
Change order addedMechanical · Δ $75,000 cost $60,000 · at_risk23d ago
Change orders1
CO CO-01Mechanical
Schedule compression — added shift
$75,000
cost $60,000
crew hours pending
Estimate ledgerRevised GP$450,00018.8% GM
DivisionOrig valueOrig GPOrig GMRev valueRev GPRev GMΔ GP
Mechanical$1,500,000$315,00021.0%$1,500,000$315,00021.0%$0
IC&E$600,000$108,00018.0%$600,000$108,00018.0%$0
Scaffolding$300,000$27,0009.0%$300,000$27,0009.0%$0
Job total$2,400,000$450,00018.8%$2,400,000$450,00018.8%$0
At-risk $75,000
Turbine
Siemens SGT6-5000F · U3unlinked — not in Radar
Labor hours — planned vs actual
CraftPlannedActualVariance% used
Lead Turbine Mechanic1200-1200%
NDE Level II Technician400-400%
Senior Turbine Mechanic2400-2400%
Crew on this project (5)Bench Board
NameRoleDates%
Javier RuizLead Turbine MechanicJul 20Aug 10100%
Andre ColeSenior Turbine MechanicJul 20Aug 10100%
Will HodgeSenior Turbine MechanicJul 20Aug 10100%
Sam PierceTurbine MechanicAug 3Aug 10100%
Iris BellNDE Level II TechnicianAug 3Aug 1050%