Steam turbine major inspection

Magnolia Utilities
Specialist · 3001 Industrial Rd, Pascagoula, MS 39581 · GE D11 steam (ST-2) · 2026-07-272026-08-31 · active
Execution phasemobilized 2026-07-27
Mobilize
Disassembly
Inspection
Repair
Reassembly
Test & commission
Demobilize
Phase 1 of 7 · Mobilize
Recent updates & change orders
Change order addedSpecialist · Δ $110,000 cost $85,000 · approved23d ago
Change orders1
CO CO-01Specialist
Diaphragm weld repair on findings
$110,000
cost $85,000
crew hours pending
Estimate ledgerRevised GP$274,00016.0% GM 0.5 pts
DivisionOrig valueOrig GPOrig GMRev valueRev GPRev GMΔ GP
Specialist$700,000$105,00015.0%$810,000$130,00016.0%+$25,000
Mechanical$600,000$114,00019.0%$600,000$114,00019.0%$0
Scaffolding$300,000$30,00010.0%$300,000$30,00010.0%$0
Job total$1,600,000$249,00015.6%$1,710,000$274,00016.0%+$25,000
Turbine
GE D11 steam · ST-2unlinked — not in Radar
Labor hours — planned vs actual
CraftPlannedActualVariance% used
Field Machinist1200-1200%
Lead Turbine Mechanic2000-2000%
NDE Level II Technician1600-1600%
Turbine Mechanic4000-4000%
Crew on this project (3)Bench Board
NameRoleDates%
Javier RuizLead Turbine MechanicAug 10Aug 31100%
Iris BellNDE Level II TechnicianAug 10Aug 31100%
Frank OttField MachinistAug 3Aug 24100%