Workload Command Center

crew we have vs work on the horizon
Gulf Turbine Servicesall divisions
$15.97Mrevised value · 7 active jobs
Budget performancemargin vs bid · labor vs plan
Margin held
16.4%
bid 16.7% · -0.3pt
Labor burned
50%
3,170 / 6,400 hrs · GP $2.63M
Schedule performancedone vs calendar par
Pace
64pt behind
Complete
22%
par 86% elapsed
Budget = margin held vs bid (fade) + labor hrs burned vs planSchedule = work done vs calendar par; behind = at risklabor over 100% = over budget, not >100% done one job, counted in each division it touches
Specialist3 jobs
$1.49M book
Budget performancemargin vs bid · labor vs plan
Margin held
17.7%
bid 16.2% · +1.4pt
Labor burned
0%
0 / 580 hrs · GP $263,000
Schedule performancedone vs calendar par
Pace
56pt behind
Complete
0%
par 56% elapsed